A floor plan already contains the quantities needed for a first estimate: floor areas, metres of perimeter, walls to finish, openings. This guide explains how to obtain them from a model, how to apply a price list and why the result is a preliminary estimate, not a quote.

Flat under renovation with cyan lines tracing the walls and a new partition

Updated on 14 October 2026 · Loto Studios

The quantities that come out of a model

QuantityUnitWhere it comes fromTypical use
Floor area per roomm²Polygon of the roomFloors, screeds, ceilings
Perimeter per roommSides of the polygonSkirting boards, cornices
Gross wall surfacem²Wall length × heightPlaster, insulation
Net wall surfacem²Gross surface minus openingsPainting, tiling, wallpaper
Internal wall lengthmSum of the internal dividersPartitions to build or demolish
Openingsnumber, m²Doors and windows placed on the wallsFrames, doors

In ShotPlan these quantities are calculated from the volumetric model and exported per room and as totals in a JSON file Available. The square metres guide explains how floor areas are measured.

From quantities to costs: the price list

A price list links each quantity to a unit price: €/m² for floors, €/m for skirting boards, €/m² for painting. The cost of an item is quantity × unit price; the total is the sum of the items. The price list can be yours, your supplier’s or a test one: the result is worth as much as the price list used.

Two rules keep the estimate honest:

  • always state the name and version of the price list next to the total;
  • call it preliminary estimate, never a binding quote: waste, site conditions, labour and discounts are not in the model.

A worked example on the demo flat

The example applies a demonstration price list to the demo project “Appartamento tipo” (69.30 m²): floors at 60 €/m² for the living room and bedrooms, 85 €/m² for bathroom and hall (tiles); internal partitions at 95 € per metre. The quantities come from the model; the arithmetic is the same the software will do when price-list costs arrive Coming soon.

ItemQuantityUnit priceAmount
Living and kitchen · floor32.03 m²60 €/m²1,921.80 €
Bedroom 1 · floor14.58 m²60 €/m²874.80 €
Bedroom 2 · floor10.62 m²60 €/m²637.20 €
Hall · floor6.79 m²85 €/m²577.15 €
Bathroom · floor5.29 m²85 €/m²449.65 €
Internal partitions17.50 m95 €/m1,662.50 €
Total6,123.10 €

Change one wall state to “demolition” and save: the model has a new revision, and the comparison between revisions is where the cost difference will appear. Today you read quantities and revisions in the demo workspace; the price list is coming soon.

What a preliminary estimate is not

  • It is not a bill of quantities according to a standard: it does not apply deductions, waste or regulatory conventions.
  • It is not a binding quote: labour, site conditions, supplies and discounts belong to whoever makes the offer.
  • It is not an accuracy guarantee: the numbers are as good as the model and the price list.

What it is: a quick, consistent and verifiable way to compare two solutions on the same model, before spending hours on the final quote.

Who uses it, and how

Construction and renovation companies use it to answer variants in the meeting; software companies take the quantities into their own estimating program with their own price lists; real estate agencies show a renovation scenario with a number next to it.

Frequently asked questions

Does ShotPlan provide the price list?

No. ShotPlan applies a configurable price list: yours, your partner’s or a test one for the demo. Market prices remain with whoever makes the offer.

Do the quantities take waste into account?

The quantities exported today are geometric: floor areas, perimeters, walls and openings. Waste and mark-up percentages are applied in the price list or in your estimating program.

Can I export the estimate to Excel?

The quantities are exported as JSON, a format spreadsheets and ERPs can read with an import. Ready-made PDF or CSV reports are not planned today; if you need them, tell us in the pilot project.